September - December
- Relocation of Duke, ConocoPhillips (DCP) pipeline.
- Site utility work continues
- South Gallery 1st Floor (largest single concrete pour during project)
- West Passage Tunnel Walls being pored
- Storm sewer lines under the tunnel.
June - August 2007
- Gallery Building basement walls, columns
- West Passage Tunnel foundations, walls, and lid
- Site Utility Work
- Rubble clearing for DCP pipeline relocation
January-March 2007
Gallery Building
• Drilled Piers & Pier Caps
• Waterproofing
• Underground Plumbing
• Grade Beams
• Elevator jack holes and pits
West Passage Tunnel
• Drilled Piers
• Grade Beams
• Storm sewer lines and structures
Central Promontory
• Mass earthwork haul-in continues
• Shaping of the back side slopes